Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. (Which of the following two statements are correct regarding subcontractors under FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
A) The Contract Data may identify parts of the Works which the Contractor is not entitled to subcontract.
B) The Contractor shall obtain the Engineer's and the Employer's prior consent to all Subcontractors.
C) If no maximum allowable accumulated value of work subcontracted is stated in the Contract Data, the Contractor shall not be entitled to subcontract the whole of the Works without prior consent of the Engineer.
D) The Contractor shall not be responsible for the acts or defaults of any Subcontractor.
2. Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)
A) Yes, because otherwise the Contractor doesn ' t have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.
B) Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor ' s Documents in the Employer ' s Requirements, as stated in Sub-Clause 5.2.
C) No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.
D) No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause
7.4.
3. The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition
1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back- to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:
" Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer
' s Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer ' s Requirements, its items of reference or Contractor ' s design of the Works for the scope part for which Subcontractor is contracted. " What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?
A) I would advise the SC not to enter this contract because the Contractor is obliged to act in accordance with good faith. A proposed paragraph like this opposes good faith.
B) I would advise the SC to enter the Contract with the request to the Contractor to delete this amendment in the Particular Conditions. If the Contractor does not agree to do so, at least the Subcontractor has tried its best.
C) I would advise the SC not to enter this contract, because Sub-Clause 4.4 describes the obligations of SC towards Contractor, but this amendment positions the SC in a vulnerable position for claims regarding all errors, faults or other Defects (whether originating from the Employer ' s Requirements or the design of the Contractor). Essentially, this means the SC becomes liable for the design part, which is within the scope of Contractor even without SC having the opportunity to review it.
D) I would advise the SC to discuss this amendment with the insurance company just to be sure there will be no transfer of risks. This amendment is mainly a consequence of the FIDIC Yellow Book structure, where the Contractor has obligations in terms of scrutinizing the Employer ' s Requirements. This amendment makes this obligation more explicit. If the insurance company has no problems with insuring the parts which will be delivered by SC to Contractor, the SC can accept this risk and enter into the subcontract.
4. (Under FIDIC Red Book (edition 1999) a notice may be delivered to which two addresses?
Choose all of the correct answers (multiple possibilities).)
A) The address of the Contractor ' s Representative.
B) The address stated in the Contract Data.
C) The address provided for by the recipient of the notice.
D) The address of the Site.
5. Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?
A) A description of the proposed design.
B) A Programme for execution of the varied work.
C) A description of the varied work.
D) Details of the resources and methods to be adopted by the Contractor.
Solutions:
| Question # 1 Answer: A,C | Question # 2 Answer: B | Question # 3 Answer: C | Question # 4 Answer: B,C | Question # 5 Answer: A |


PDF Version Demo






We are confident about the products and aim to help you pass with ease. In case of failure, we will provide a no hassle full money back guarantee for the purchasing fee.
1097 Customer Reviews
Quality and ValueITbraindumps Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.
Tested and ApprovedWe are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.
Easy to PassIf you prepare for the exams using our ITbraindumps testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.
Try Before BuyITbraindumps offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.